Skip to content
HM Fire Service Inspectorate in Scotland
  • Home
  • About us
    • About us
    • What we do
    • Our team
    • Our values
    • Our history
  • Our scrutiny
    • Our scrutiny
    • Inspection process
    • Service Delivery Area inspections
    • Local Area inspections
    • Thematic inspections
    • Other Focused Inspections
    • Significant events
    • Non-domestic fire safety
  • Publications
  • Contact
  1. Home
  2. Publications
  3. The Scottish Fire and Rescue Service Command and Control Mobilising System (CCMS)
  4. Inspection Findings - Other factors

The Scottish Fire and Rescue Service Command and Control Mobilising System (CCMS)

Related Downloads

  • The Scottish Fire And Rescue Service Command And Control Mobilising System (CCMS)
    PDF file, size 230.3 KB
Other Focused Inspections

18th April 2023

HM Fire Service Inspectorate (HMFSI) report on an inspection which examined the challenges and future of the Scottish Fire and Rescue Service’s Command and Control Mobilising System.
  • Introduction
  • Overview of Inspection Outcome
  • Background - Site relocation
  • Background - Functions
  • Inspection Findings - Why a new mobilising platform was necessary
  • Inspections Findings - The system specified
  • Inspection Findings - The performance and resilience of the existing CCMSs
  • Inspection Findings - Contingency for system interruption
  • Inspection Findings - Other factors
  • The Way Forward
  • Conclusion
  • Glossary
  • Appendix
  • Footnotes

  • Introduction
  • Overview of Inspection Outcome
  • Background - Site relocation
  • Background - Functions
  • Inspection Findings - Why a new mobilising platform was necessary
  • Inspections Findings - The system specified
  • Inspection Findings - The performance and resilience of the existing CCMSs
  • Inspection Findings - Contingency for system interruption
  • Inspection Findings - Other factors
  • The Way Forward
  • Conclusion
  • Glossary
  • Appendix
  • Footnotes

Inspection Findings - Other factors

Technology Changes and Key Dates

53. There are some pending key dates, which impact on the priority to modernise the current CCMS at all three OCs.

The implications of the ISDN (Integrated Services Digital Network) switch off means that all three current CCMS will not be compatible with replacement technology from December 2025. Furthermore, the Home Office is delivering a new Emergency Services Network (ESN) which will replace the current Airwave radio system used by Emergency Services, the deadline for which for SFRS is also anticipated to be towards the end of 2025.

54. If the Systel Contract had been successfully implemented on time, technology changes would have been accommodated in a new system. The impact of a delay to implementing a replacement CCMS results in an increased risk of having equipment in place which is not compatible with the ISDN switch off and ESN implementation.

Consideration of electricity outages

55. SFRS has included in its overall resilience planning the consideration of power outages. Each Standby Control has back-up generators in place which are tested regularly. In the event of a mains electricity outage, in order to limit the impact of a change over from mains electricity to fuel powered generator supply, there has been investment in the UPS (uninterrupted power supply) backup systems at OCs. This has been carried out with the aim of reducing the risk of a potential ‘cold start’ of a server. A ‘cold start’ is an unplanned shut-down of a server, which would then require to be restarted from cold. There are concerns due to the fragility of systems that a cold start of a server could result in a significant system failure which may be difficult to recover from.

Staffing Levels

56. The OCs each have different workload demands and therefore different staffing arrangements. Staffing levels at all three OCs have been impacted as a result of staff turnover and absence. There has been a reliance on overtime on a regular basis to be able to maintain minimum staffing levels in OCs.

Previous
Inspection Findings - Contingency for system interruption
Next
The Way Forward
Accessibility
Data Protection
Freedom of Information
Cookie Policy
Site Map
© 2025 HM Fire Service Inspectorate in Scotland

We use the necessary cookies to make our site work. We'd also like to set analytics cookies that help us make improvements by measuring how you use the site. These will be set only if you accept.

For more detailed information about the cookies we use, see our Cookie Policy.